August 12, 2026
Earnings Call - 12.08.2026
Ashoka Buildcon Limited
To, To,
The Manager, The Manager,
The Department of Corporate Services The Listing Department
BSE Limited National Stock Exchange of India Limited
Floor 25, P. J. Towers, Exchange Plaza, Bandra Kurla Complex,
Dalal Street, Mumbai – 400 001 Bandra (East), Mumbai – 400 051
Scrip Code
Equity: 533271 Scrip Symbol: ASHOKA
Debt Codes
CPs –730851/731112/731435/731487/732069/732127; and
NCDs - 976190 / 976191 / 976192
August 18, 2026
Sub
Call Transcript
Please find enclosed herewith the copy of transcript of the Earnings Call held on August 12, 2026 in respect of unaudited Standalone and Consolidated financial results for the quarter ended June 30, 2026.
Kindly take the matter on your record.
Thanking you,
For Ashoka Buildcon Limited
Manoj A. Kulkarni
(Company Secretary)
ICSI Membership No.
FCS – 7377
Regd. Office
S. No. 861, Ashoka House, Ashoka Marg, Vadala, Nashik – 422 011, Maharashtra, India hhhhTel. + 91 253 6633705hhhhFax +91 253 2236704 hhhh www.ashokabuildcon.com
CIN
L45200MH1993PLC071970
“Ashoka Buildcon Limited
Q1 FY27 Earnings Conference Call”
August 12, 2026
E&OE - This transcript is edited for factual errors. In case of discrepancy, the audio recordings uploaded on the stock exchange on 12th August 2026 will prevail
MANAGEMENT
• Mr. Satish Parakh – Managing Director – Ashoka Buildcon Limited
• Mr. Paresh Mehta – Chief Financial Officer – Ashoka Buildcon Limited
MODERATOR
• Mr. Mudit Bhandari – IIFL Capital
Page 1 of 20
Ashoka Buildcon Limited
August 12, 2026
Moderator
Ladies and gentlemen, good day, and welcome to the Ashoka Buildcon
Q1 FY27 Earnings Conference Call hosted by IIFL Capital. As a reminder, all participant lines will be in the listen-only mode and there will be an opportunity for you to ask questions after the presentation concludes. Should you need assistance during this conference call, please signal an operator by pressing star then zero on your touch-tone phone. Please note that this conference is being recorded.
I now hand the conference over to Mr. Mudit Bhandari from IIFL
Capital. Thank you, and over to you, sir.
Mudit Bhandari
Thank you so much. Good afternoon, everybody. On behalf of IIFL
Capital, I welcome you all to first quarter FY27 earnings conference call of Ashoka Buildcon Limited. From the management, we have Mr.
Satish Parakh, Managing Director; and Mr. Paresh Mehta, Chief
Financial Officer.
With this, I would request Satish sir to start with his opening comments, and then we can open the floor for question-and-answer.
Thank you, and over to you, sir.
Satish Parakh
Thank you, Mudit. Good afternoon, everyone. A very warm welcome to all of you joining us for Ashoka Buildcon earnings conference call for the quarter ended 30th June 2026. Joining me on today's call are our
CFO, Mr. Paresh Mehta, along with our Investor Relations Advisors from SGA.
I hope everyone has had the opportunity to review our financial results and investor presentation, which have been uploaded on the stock exchanges and the company's website. Let me begin by giving you a brief perspective on industry environment and then take you through some of the key developments of Ashoka during the quarter.
Q1 FY27 has started on a mixed note for infrastructure sector. On one hand, the domestic highway awarding environment continues to remain subdued. On the other hand, we are seeing encouraging
Page 2 of 20
Ashoka Buildcon Limited
August 12, 2026 opportunities emerging in the areas of railways, power transmission, distribution and international infrastructure.
In the highway segment, the pace of fresh awarding continues to be below the levels we have seen historically. NHAI awarded only around
5 kilometers of projects in June compared with 102 kilometers in May, while construction activity in June declined 32% year-on-year to around 274 kilometers. For the first 2 months of FY27, construction stood at approximately 638 kilometers, which is around 34% lower year-on-year.
So while we remain positive on the long-term fundamentals of India's road infrastructure, we believe the sector is currently going through a period, where the focus is shifting from simply awarding more kilometers to ensuring that projects are properly appraised, land is made available and execution can proceed efficiently.
For us, this makes diversification particularly important. At the same time, the medium- to long-term opportunities in infrastructure remains strong. The Indian budget has provided a significant push to the railway sector with a record capital expenditure allocation of approximately INR2.93 lakh crores.
The government has also announced 7 new high-speed rail corridors covering around 4,000 kilometers with an estimated investment potential of INR16 lakh crores, along with 2,052 kilometers dedicated freight corridor between Dankuni and Surat. This is important because the opportunity in railways is no longer limited to traditional track construction.
It increasingly spans over electrification, signaling, safety systems, freight infrastructure, station development and other specialized EPC requirements. For Ashoka, this creates an opportunity to leverage our existing execution capabilities and participate in infrastructure spending beyond the traditional road segment.
Page 3 of 20
Ashoka Buildcon Limited
August 12, 2026
The power transmission and distribution segment is another area, where we see long structural growth. India is adding renewable energy capacity at a rapid pace, but the success of this transition depends equally on the ability to evacuate and transmit that power to consumption centers. This is driving significant investment into state transmission systems and energy corridors.
Let me now highlight key business developments for Q1 FY27 which was marked by international and non-road wins, while domestic road awarding stayed muted. We believe this is an important development because it demonstrates that our diversification strategy is beginning to provide us with alternative avenues for growth, while the domestic highway cycle remains subdued.
In Guyana, we received a letter of award from Central Housing and
Planning Authority for the 4 laning of Versailles-Parika Highway in
Region 3. The project is valued at USD 35.42 million, around INR328 crores.
This award is particularly encouraging because it further strengthens our international road infrastructure portfolio in the South America.
In Chhattisgarh, our joint venture received a letter of award from
Chhattisgarh State Industrial Development Corporation for the development of Gems and Jewellery Park in Raipur under the PPP mode.
The project involves a premium of approximately INR112.4 crores with Ashoka holding 51% stake in the joint venture. The project has a
5-year construction period and a 30-year lease extendable to 90 years.
What makes this project strategically relevant is that it represents our entry into industrial park development and therefore adds another vertical to our infrastructure portfolio.
As a part of our portfolio streamlining, we diluted our stake in Ashoka
Purestudy Technologies Private Limited from 59% to 39.33% pursuant
Page 4 of 20
Ashoka Buildcon Limited
August 12, 2026 to a preferential allotment resulting in a classification from subsidiary to an associate company.
Coming to the order book status, the company received 2 new project orders as discussed from Central Housing and Planning Authority
Republic of Guyana INR328 crores in Chhattisgarh State Development
Corporation, Gems and Jewellery Park of INR450 crores.
As on 30th June, our order book stands at INR15,251 crores, excluding order received after 30 June, that is ~INR450 crores. The breakup of the order book is road and railway comprised of around INR9,648 crores, which is 63.3% of the order book. Among the road order book,
HAM projects are to the tune of ~INR1,500 crores.
And EPC is worth around ~INR6,780 crores and railway is around
INR1,346 crores. Power T&D accounts for around INR5,066 crores, which is approximately 33.2% of the total order book. The building
EPC segment is INR536 crores, which is 3.5% of the total order book.
With this, I would now request Mr. Paresh Mehta, CFO, to present the financial performance. Thank you.
Paresh Mehta
Thank you, sir. Good afternoon, everybody. Starting with the standalone numbers; For Q1 FY27, total income stood at INR1,320 crores as compared to INR1,339 crores in Q1 FY26, flat year-on-year.
EBITDA for the quarter stood at INR126 crores down to 17% Y-on-Y with EBITDA margin of 9.5%.
Profit after tax stood at INR31.5 crores against INR30.6 crores during
FY26 Q1, up 3%, Y-on-Y. Our revenue contribution for each segment for Q1 FY27 is as follows; Road EPC contributed 49.3%, Road HAM contributed 10.2%, Power T&D contributed 18.4%, railway stood at
11.5% and other segments like building EPC and others contributed to
10.7%.
Page 5 of 20
Ashoka Buildcon Limited
August 12, 2026
Coming to consolidated numbers; Total income for Q1 FY27 stood at
INR1,534 crores as compared to INR1,937 crores in Q1 FY26, this is seeing a 21% de-growth largely contributed by monetization of BOT and HAM projects in the Q3 FY26. EBITDA for the quarter stood at
INR292 crores, down 55% year-on-year with EBITDA margin at
19.0%, again due to monetization of HAM and BOT assets.
Profit after tax stood at INR127 crores during Q1 FY27. In Q1 FY27, our BOT division, the company recorded a gross total toll collection from Jaora-Nayagaon road project of INR75 crores, up by 8% year-on- year.
With this, we now open the floor for question-and-answers. Thank you.
Moderator
Thank you very much. We will now begin with the question-and- answer session. Will take the first question from the line of Aditya
Sahu from HDFC Securities Limited.
Aditya Sahu
I had a few queries and data points, if you can help me with. This is pertaining to the bid pipeline. What would be the bid pipeline that we have right now? And if you can throw some light on where are we sort of bidding the projects considering that road awarding has been next to nothing. So if you can throw some light on which sectors and what is the amount of bid pipeline?
Satish Parakh
So if we see the bid pipeline, NHAI and MoRTH alone is throwing up around INR1 lakh crores of bids to be coming in. And if we see states then about INR25,000 crores bids are on the pipeline. Other than this, railways is there, which is throwing around INR50,000 crores of bids, which are already now under pipeline. Other than this, power T&D and renewable energy sector are there where we are also bidding for EPC.
Aditya Sahu
Okay. So I mean what would be the value of project that is bidded for right now as on date if you can help me with that?
Page 6 of 20
Ashoka Buildcon Limited
August 12, 2026
Satish Parakh
So wherever we have bid and bids are not yet open is around INR8,000 crores.
Aditya Sahu
Okay. Understood, sir. And in terms of the revenue, EBITDA and the order inflow guidance, if you can provide that?
Satish Parakh
So guidance, we are lowering down from 20% to between 10% to 15% because this quarter has been flat due to various reasons and various uncertainties, particularly supply chain. So we feel the overall performance will be able to touch between 10% to 15% growth. And order book provided...
Aditya Sahu
From earlier 20% I think because you had mentioned the 20% growth.
Yes.
Satish Parakh
Yes, 20% was earlier...
Aditya Sahu
Okay. And on the EBITDA margin front and the order inflow?
Satish Parakh
Order inflow will be to the tune of INR6,000 to INR8,000 crores. We have already got INR800 crores in Q1. We are L1 in around INR1,800 crores. That will materialize in Q2. And further, we should be able to bag around INR6,000 to INR8,000 crores in balance 3 quarters.
Aditya Sahu
Okay. Okay. So INR6,000 to INR8,000 crores?
Satish Parakh
Q1 has been good in that way. Q1 has been good. INR780 crores plus
L1 in INR1,800 crores.
Aditya Sahu
And then the margin guidance standard was the same level, 9.5% to
10.5% roughly that we were targeting?
Paresh Mehta
For the year around, probably we will touch that once we ramp up our revenues in the next H2 rather. H1 will continue to remain subdued, but H2 will definitely ramp up and there we'll catch up with 9.5% of
EBITDA based on whatever we are spending for the new projects which are taking off, where initial establishment expense is now being
Page 7 of 20
Ashoka Buildcon Limited
August 12, 2026 incurred, mobilization, then we had ramp up in the H2 and margins also will look better.
Aditya Sahu
Understood, sir. On the HAM equity requirement, what would be the investment amount that we have done till date? And how much would be the pending contribution on a year-on-year basis?
Paresh Mehta
So for the coming years, for '26-'27, we will have to invest INR 179 Cr on the existing HAM projects including Bowaichandi project. And for
'27-'28 and '28-'29 it would be INR 72 crores each. And investment up to June, the six HAM projects is to the tune of almost INR638 crores.
.
Aditya Sahu
Okay. Understood, sir. I mean earlier we were targeting on the sale of the 6 SPVs. Our initial plan was, I understand that this was 4 assets by the June quarter and 2 assets by the December quarter. And now I think that we have revised that. So all the assets are being sold by
September '26. Is that how the revised timeline looks like and why the revision timeline from June to September?
Paresh Mehta
So as we said, 4 assets, we expect to clear by Q2 revised from Q1, largely because certain compliances to be done for handing over the project to the investors. So that presently there is some delay in handing over. Some compliances we take on but it is on track and we expect that by September end or first part of October definitely we should be able to get the money in.
Aditya Sahu
And that is for all 6 assets you're referring to?
Paresh Mehta
For the 4 assets, the other 2 assets need some time. Because there are duty and other compliance to be done at those projects, which will happen by December and may be Q4, we'll be able to demonstrate the sales.
Page 8 of 20
Ashoka Buildcon Limited
August 12, 2026
Aditya Sahu
Understood, sir. And the realization, how much are we realizing from these assets? If you can -- the 4 assets and the 2 assets, respectively, if you can give those numbers?
Paresh Mehta
The total price which was offered by them, when we disclosed was around approximately INR1,100 crores. And we expect to realize approximately that for a bit of time.
Aditya Sahu
Okay. Pardon, if you could repeat the number?
Satish Parakh
INR1,100 crores.
Aditya Sahu
INR1,100 crores would be for the 4 assets.
Paresh Mehta
For the 6 assets.
Aditya Sahu
For the 6 assets. Okay. And for the 4 assets that we are planning to sell by September?
Paresh Mehta
Approximately INR700 crores.
Moderator
We have the next question from the line of Vaibhav Shah from JM
Financial.
Vaibhav Shah
You mentioned that EBITDA margins would be 9% to 9.5% for the entire year?
Paresh Mehta
Yes.
Vaibhav Shah
So we are lowering the guidance?
Paresh Mehta
Yes, by 0.5% because we lost something in this quarter, which will not totally recover for the balance 3 quarter. So we were in the range of around 2 digits at the start of the year. We will be at roughly 0.5% short of that.
Vaibhav Shah
Okay. So secondly, margins without other income was 7.2% in first quarter. So any one-offs in the margin? Any provisions or something?
Page 9 of 20
Ashoka Buildcon Limited
August 12, 2026
Paresh Mehta
No, nothing very significant vis-a-vis as compared to previous year.
But largely because we have mobilized a lot of new administrative and employees and other costs for the new verticals where in the initial phase those costs have been loaded in this quarter. So they get rationalized over the coming quarters.
Vaibhav Shah
Sir, on the debt side, we have roughly INR2,100 crores of debt. So partly it is from the subsidiaries. So can you give the breakup of the subsidiary debt and the breakup of interest cost, third-party and what you are paying to subsidiary in 1Q?
Paresh Mehta
So interest cost paid to the subsidiaries is INR17 crores for this quarter.
Balance is all third-party interest paid, including NCDs, working capital, term loans and equipment loans and also interest on mobilization advance, which is to the employers.
Vaibhav Shah
Okay. Sir, once the assets are monetized, then what could be the debt number, at least the third-party debt?
Paresh Mehta
Third-party debt would be approximately in the range of, as we have guided, around INR500 crores to INR600 crores.
Vaibhav Shah
And what is the amount, right? So we won't be reducing the debt from subsidiaries in future?
Paresh Mehta
So these debt need not be reduced because they are typically free cash flows of our subsidiaries. And they are typically 100% subsidiaries of
Ashoka Buildcon. So they may continue to be part of the resources for
Ashoka Buildcon. So on the consol level, they will get knocked off.
But otherwise, it's not a third-party outflow for the consol.
Vaibhav Shah
At stand-alone level it will hit the interest cost?
Paresh Mehta
Yes, it's a stand-alone cost. It doesn't have a third-party cost.
Page 10 of 20
Ashoka Buildcon Limited
August 12, 2026
Vaibhav Shah
If you include the third-party debt and the debt from subsidiaries, so maybe post monetization, the debt could be around INR1,000 crores, including the debt from subsidiary?
Paresh Mehta
Around say INR1,100 crores, around approximately INR700 crores would be third-party debt. So around, say, INR1,200-odd crores.
Vaibhav Shah
Okay. And sir, on interest cost side, we have seen reduction to INR60 crores in this quarter. So incrementally, it will further come down to maybe end the year by around INR50-odd crores?
Paresh Mehta
Yes, definitely, we expect on 2 counts. One is realization of our WIP working capital receivables and WIP in our power sector, which is due to be collected in the next 2 quarters as well as monetization of assets will typically also reduce debt.
Vaibhav Shah
Okay. Sir, when are we expecting the for AD for Bowaichandi HAM?
Satish Parakh
October first week, we should expect appointed date.
Vaibhav Shah
So maybe 15%, 20% work only would happen for this year?
Satish Parakh
This year will be around 15%.
Vaibhav Shah
Okay. And sir, when will work start for the newer projects Mithi River,
Guyana and Angola?
Satish Parakh
Mithi has also started now. And Guyana, we are already present, the work is ongoing. Angola will take some time to start, maybe another 2 months.
Vaibhav Shah
Okay. And sir, lastly, you mentioned that the total cash flows from monetization will be roughly INR1,100 crores. So earlier it was
INR1,150 crores. So is that lowering down of the number?
Paresh Mehta
No, it's INR1,150 crores, just a rounding off.
Page 11 of 20
Ashoka Buildcon Limited
August 12, 2026
Vaibhav Shah
Okay. And sir, last, the assets which you have already monetized, of that, part amount was pending, some INR50 crores for BOT and
INR90 crores for HAM. So has that been received now?
Paresh Mehta
No, we are in the process of receiving. We have almost received around 30% of it and balance we are in the process of getting it. It is in process, there are certain compliances which needs to be done to get it done. So we're waiting for that.
Vaibhav Shah
And of this INR1,150 crores, entire would be received this year or part would be stuck?
Paresh Mehta
As I said, by Q2, the 4 assets and by Q4, the balance 2 assets, that's what our target would be.
Vaibhav Shah
I mean would there be any holdback amount of INR1,150 crores?
Paresh Mehta
Didn't get it.
Vaibhav Shah
So in the previous 2 deals for 5 BOT and 5 HAM, part amount roughly
INR150 crores was hold back. Which we're expecting to receive the balance portion now. So of INR1,150 crores, would there be any holdback or the entire money will be received in this year?
Paresh Mehta
So there could be holdbacks, small holdbacks in the range of INR30 crores, INR40 crores. I mean that will depend once we get to very close to the transaction. So it's more of compliance, which will be there. So I really cannot pinpoint the number at this moment.
Vaibhav Shah
Okay. And sir, lastly, what would be the capex for 1Q and the target for FY27?
Paresh Mehta
So capex for this quarter was approximately INR25 crores, of which
INR7 crores was for our international projects and balance was for domestic. Target, as we said, was approximately INR125 crores for the whole year.
Page 12 of 20
Ashoka Buildcon Limited
August 12, 2026
Vaibhav Shah
Margins would be weaker for this year, next year could it be in 10%,
10.5% range for FY28?
Paresh Mehta
We should expect that as projects which are there, typically would throw a margin of 10.5%, 11%. So we should definitely expect margins to improve over a period of time.
Moderator
We have the next question from the line of Vasudev from Nuvama.
Vasudev Ganatra
Most of the questions are answered. I just want to know where are we on monetization of Chennai ORR and Jaora-Nayagaon? Any thoughts on that?
Paresh Mehta
So on both the projects, we have potential investors who have shown interest. They are working on one of the projects, they are also working on the diligence part of it. We expect Chennai ORR could happen by the year-end. We still need to freeze on the investor. And Jaora-
Nayagaon, either by March end or by next year first half. It has more of a process to be driven at the compliance from the authority, but we expect that by Q1, we should be able to aggressively monetize.
Moderator
We have the next question from the line of Daksh Prashar from
Desvelado Research.
Daksh Prashar
I just have one question. So we diluted our stake in Ashoka Purestudy
Technologies from 59% to 39%. Would you please shine some light on what was the rationale behind that exit?
Paresh Mehta
We have diluted and we have brought in a strategic partner who will help us in execution of projects which we have taken at Purestudy level. So the intent is to create more value at the SPV level for our stakes.
Moderator
We have the next question from the line of Bhavin Modi from Anand
Rathi.
Page 13 of 20
Ashoka Buildcon Limited
August 12, 2026
Bhavin Modi
Sir, I wanted to know what is the order book that is lying at the SPV level? Like I believe few of our order book are at the SPV level. Can you just help with the number?
Paresh Mehta
So at the SPV level presently, couple of orders are lined. We have not pulled the number exactly. Maybe if you can come offline. Or maybe by the end of this call, I can give you that number.
Bhavin Modi
Okay. Secondly, sir, we have been recently seeing the share of the international book has been increasing. So what is the first thing the strategy behind that? Is it because the awarding is lower happening in the road side or is it because the margins are better in the international side? And just how are the international orders different from the domestic orders?
Satish Parakh
So basically, internationally, we are just increasing our presence in various country. We have an independent vertical for international.
And margins and competition will vary from country to country.
Presently, we are working in 7 countries. We plan in going ahead to work around in 10 countries.
Bhavin Modi
Okay. And any specific geographies that you're targeting not to enter?
Satish Parakh
Not to enter geographies are not yet that well listed. But what we have been working in these 7 geographies, and we may add another 2, 3 geographies. It's all, we evaluate when the opportunities feel right.
Bhavin Modi
Right. And sir, lastly, how are you seeing the road awarding happening this year? Obviously, till date, there hasn't been any remarkable awarding that has happened.– And the NHAI has come up with a list of
113 highways. So how are we seeing in terms of the competition and in terms of the awarding happening by the end of this year?
Satish Parakh
So Q3, Q4, we expect good awarding to happen. And off late NHAI is also going for bigger sized packages. So that will definitely rationalize the competition also. And we will have healthy competition amongst
Page 14 of 20
Ashoka Buildcon Limited
August 12, 2026 good players. Size of the projects are going for the larger sized projects.
Bhavin Modi
Right. sir, and the last thing is NHAI is coming up a big ticket BOT orders. There are few BOT orders which are even of INR5,000 crores plus. So are we looking to participate in the bids of such orders?
Satish Parakh
So we have been evaluating these BOT orders also. So project by project, we need to take a call. So wherever we are comfortable and we are sure about traffic and execution, we may participate.
Moderator
We have the next question from the line of Mudit Bhandari from IIFL
Capital.
Mudit Bhandari
Sir, we have roughly around INR150 billion to INR153 billion order book across road, power and building. You mentioned some delays in collection from Power T&D side. So how is this across our segment or across the client for, let's say, for 1Q or 4Q? And how has the working capital been?
Paresh Mehta
What was the first part? I got the second part, which is impact on working capital. Could you repeat the first part of the question?
Mudit Bhandari
Yes, in terms of collection, how it is across the sector or across the clients? Anything particularly hurting the execution?
Paresh Mehta
So execution is not hurt by collection, but collection was getting increased in the Power T&D sector, which will now get realized in the next couple of quarters. So we expect that that should rationalize by this year-end 4Q. And most of the payment should be in, which is today locked up in working capital and debtor that is unbilled revenue and debtors. The roads and other they are almost in sync with what is planned and as per milestone.
Mudit Bhandari
Got it, sir. And any Q-o-Q impact on working capital from March to
June?
Page 15 of 20
Ashoka Buildcon Limited
August 12, 2026
Paresh Mehta
Any?
Mudit Bhandari
Working capital differential from March to June?
Paresh Mehta
Yes. So approximately INR250-odd crores has been infused in March for the new projects which have taken off where billings yet to start. So the investments have happened in those sectors, advances paid to contracts for new contracts. So that way it has increased, but it is all as planned.
Mudit Bhandari
Got it, sir. And when we say our bid pipeline across states, railways and Power T&D as well as real renewables, so any particular projects that you are aiming for or in particular, let's say, segment, whether it is more concentrated towards, let's say, within states, let's say, roads or -- so basically trying to identify some focus areas among where we will be bidding?
Satish Parakh
We have strategic focus areas. We definitely cannot disclose.
Mudit Bhandari
Got it, sir. And any big projects that you want to highlight that are coming up for bidding?
Satish Parakh
So there are large projects coming up, NHAI is coming up in UP, very big 4 projects. There is a pipeline in NHIDCL in Northeast. There are projects coming up in Hyderabad. So these all are completely like
INR1 lakh crores when I say order book, it's all part of that.
Moderator
We will take the next question from the line of Vasudev from Nuvama.
Vasudev
Yes, sir. On this Gems and Jewellery Park, what is the revenue that we can expect on a per annum basis from here? Gems and Jewellery Park project, which we got. So what kind of revenues can we expect from this project?
Paresh Mehta
So this is, as we said, it's a contract of INR450 crores to be executed in the next 5 years, where we can take almost around INR100 crores per year.
Page 16 of 20
Ashoka Buildcon Limited
August 12, 2026
Vasudev
Okay. And we also got this order from Guyana?
Paresh Mehta
From Guyana. What did you say?
Vasudev
So the construction of 4 lane highway order that we got, what is the value of this order like in rupees terms?
Satish Parakh
INR338 crores. INR338 crores is the value.
Moderator
We take the next question from the line of Aditya Sahu from HDFC
Securities Limited.
Aditya Sahu
Just one question over here. I see that because our order book is increasing on the overseas front. Related to that, I wanted to understand from a revenue standpoint, how is our revenue sort of bifurcated geographically, if you can help me with that, how much is from India, how much is from other countries, if you can provide the bifurcation? At least for the Q1 part?
Satish Parakh
In Q1, it is around INR1451 crores from out of India.
Satish Parakh
INR1451 crores.
Aditya Sahu
INR1451 crores. And so from the INR1451 crores, like do we have the geographical bifurcation from where are we getting this?
Satish Parakh
So 80% of it is from Guyana only.
Moderator
We have the next question from the line of Vishal Periwal from PL
Capital.
Vishal Periwal
Sir, with respect to the Chhattisgarh Industrial Development
Corporation, but I mean, in terms of the JV as a partner, we are working with a 51% stake. So can you give some highlight in terms of what exactly is the business model out here? Will it be on a sale or a lease? And second, what are the investments that we are planning for this particular LOA?
1 Mentioned as INR 260 crores on the call, however, the correct figure is INR145 crores
Page 17 of 20
Ashoka Buildcon Limited
August 12, 2026
Paresh Mehta
So this is largely kind of industrial park kind of gems and Jewellery
Park development, where approximately 9 acres has been given to us for development, of which 30% has to be used for use of gems and jewelleries. The intent as we said, it's to develop and it's a lease for 30 plus another 60 years. So total 90 years lease would be available on this project. And the intent is to develop the project and sell the project on a long lease basis, all the assets created over the next 5 years.
Vishal Periwal
Okay. And what do we plan to invest in this from our side as a 51% stake?
Paresh Mehta
So presuming it's everything sold off. So it's typically a project to the size of around, say, INR1,000-odd crores, which will be spent over the
5 years and recovered in that similar time.
Vishal Periwal
Okay. And remaining stake is with the state government in this?
Satish Parakh
So it is with private party, not the government.
Moderator
We have the next question from the line of Mudit Bhandari from IIFL
Capital.
Mudit Bhandari
How much equity have you invested in Jaora-Nayagaon and Chennai
ORR?
Paresh Mehta
In Jaora, all parties invested total INR278 crores as face value of equity at the start of the project when the project was developed. The invested value of ours after acquiring stakes are approximately INR
418 crores. And in Chennai ORR, all parties invested approx. INR200 crores. The effective cost of us after consolidation today is INR300 crores for 100% stake.
Moderator
We will take the next question from the line of Ziyad Mukaddam from
Ashika Institutional Equities.
Ziyad Mukaddam
Could you please guide us on how much revenue will be booked from the Bowaichandi to Guskara, Gaimukh to Payegaon, Kundalika Creek
Page 18 of 20
Ashoka Buildcon Limited
August 12, 2026
Bridge and Flyover Sion Panvel Highway in FY27, if possible, if you could quantify how much revenue booking will happen in FY27?
Paresh Mehta
Let me take it offline, because it's quite a granular number. We do have it, but not offhand.
Moderator
We have the next follow-up question from the line of Vasudev from
Nuvama Wealth.
Vasudev
Sir, I just wanted to confirm in Q1, we received 3 orders. The Guyana one is INR338 crores, Gems and Jewellery Park is INR450 crores and
Angola is INR684 crores. That's right, sir, right?
Satish Parakh
Angola was declared last year. Other 2 are in this quarter.
Moderator
We have the next question from the line of Vaibhav Shah from JM
Financial.
Vaibhav Shah
Standalone level interest cost was roughly INR313 crores for FY26. So for FY25, it should be closer to INR200-odd crores?
Paresh Mehta
Close to what number?
Vaibhav Shah
INR210 crores?
Paresh Mehta
Yes, it should be in the range of around INR225 crores or INR225 crores to INR240 crores.
Vaibhav Shah
And for '28, it should go below INR200 crores? As money would come to...
Paresh Mehta
Yes, exactly.
Vaibhav Shah
So what could be the range?
Paresh Mehta
It will all depend on how much business is executed, turnover. So it will be in the range of approximately INR200 crores, INR210 crores, assuming there is a increase in turnover in the next 2 years.
Page 19 of 20
Ashoka Buildcon Limited
August 12, 2026
Moderator
Thank you very much. Ladies and gentlemen, we will take that as the last question. And that concludes the question-and-answer session. I now hand the conference back to the management for the closing comments.
Paresh Mehta
We hope that all queries have been answered. For any further information or query left out, you could approach us or our Investor
Relations agency, SGA. And thanks, everybody, for attending the call.
Thank you.
Satish Parakh
Thank you. Thank you, everyone.
Moderator
Thank you, members of the management. On behalf of IIFL Capital, we conclude this conference. Thank you, everyone, for joining with us today, and you may now disconnect your lines.
Page 20 of 20